Update on the Dock Construction

Construction of Dock 3 is nearly complete. It will join its brothers Dock 1 and Dock 2 within days.

The harbor focus will now change to:

  • more demolition of old docks
  • preparing for electrical and water outlets on all docks
  • preparing for the installation of Dock 4 and Dock 5. Recall that the installation is scheduled for late March.

When (not if) the water level reaches 524′, we can complete the attachment to the lakewall and addition of ramps. Projected at Feb 10-20 timeframe.


 